A 183,971-square-foot warehouse on E. Division Street seeks annexation Thursday, and city planners oppose its land use change. The downtown rezoning returns too.
A warehouse that is already standing on E. Division Street wants to be annexed into Mt. Juliet. The Mt. Juliet Regional Planning Commission takes up the request at 6:30 p.m. Thursday at City Hall, 2425 N. Mt. Juliet Road.
City planners say the city’s land use plan does not support it. The same agenda brings back the downtown Town Center changes, which have had no Board of Commissioners vote yet.
Why a finished warehouse is asking to annex
The project is called Golden Bear West, formerly E. Division Street Logistics, at 1271 E. Division St. It sits outside the city limits today.
Wilson County approved it as an industrial warehouse, according to the city planners’ Nov. 19 staff report. During development, the report says, the sewer provider the project had lined up “would be unable to adequately provide sewer services.” The applicant first asked to get city sewer service without joining the city. When told that was not available, it chose to seek annexation.
“It should be noted that construction has already commenced on the project,” the report says. It notes that the building “has already been constructed” with the exterior materials now being requested.
The report gives these details:
- 11.79 acres, with one warehouse of about 183,971 square feet
- a building height of 40 feet, under the 50-foot limit
- 192 parking spaces, against the 68 the code requires, “a multitude of tractor trailer spaces” among them
- two driveways onto E. Division Street
- no tenant named; the planners say the many dock doors point to a distribution or warehouse use
If annexed, the property would be in District 3, represented by Commissioner Scott Hefner.
What city planners say
The city’s future land use map shows the whole property, and the land around it on every side, as mixed use. The applicant wants it changed to light industrial and rezoned to I-R PUD, the city’s restrictive industrial zoning.
“Staff cannot support the request for the land use plan amendment,” the report says.
The applicant asked for four waivers. Planning staff do not support any of them:
- cutting the required 100-foot open yard to 50 feet on the east side, next to homes, with a wall inside it
- a full waiver from the city’s brick and stone rule, using painted concrete tilt-up panels for about 94% of the walls
- a narrower landscape buffer along the west property line
- counting the existing trees as the buffer on the east side
If the commission sends a positive recommendation anyway, the planners list conditions. Among them:
- widen E. Division Street to three lanes along the site, with tapers at each end
- build a sidewalk at least 6 feet wide along the frontage
- cut the parking to what the code requires
- keep light at 0.5 foot-candle or less at the homes’ property lines
- the developer pays for the sewer extension that serves the site
City engineers also flagged the name. “The development has no frontage on Golden Bear Gateway,” their comments say, so the name “could create confusion.”
Where the vote stands
The land use change itself is a separate ordinance. At the commission’s Sept. 17 meeting, a motion to send it to the board with a negative recommendation failed. The six members present voted no and two were absent, the minutes show. The applicant asked to defer the annexation, the plan of services and the rezoning to Thursday.
The Board of Commissioners deferred the land use ordinance at the start of its Nov. 9 meeting, the city’s legislative record shows. The commission only recommends; the board makes the final decision on all four items.
Downtown Town Center is back
The two downtown requests also return Thursday:
- a land use change to Town Center for 68 W. Caldwell St. and land on N. Mt. Juliet Road
- a rezoning to CTC, Commercial Town Center, for parcels on E. Hill Street, E. and W. Caldwell, W. Division Street, Third Avenue and N. Mt. Juliet Road
On Sept. 17, motions to send both to the board with a negative recommendation failed, also 0-6, the minutes show. The land use change was listed in the city’s notice for the board’s Nov. 9 hearing but was not on that night’s agenda. We covered the plan and the city’s $8.08 million land sale behind it in our downtown Mount Juliet story.
The planners’ new staff report asks the commission to forward any conditions to the board with its recommendation. Planning and engineering had no comments.
Pocket parks in new subdivisions
The commission will also review a zoning change that would require pocket parks in every new single-family subdivision, on top of the playgrounds the code already requires. The staff report recommends approval.
| Subdivision size | Pocket parks required |
|---|---|
| Up to 100 homes or 100 acres | 1 |
| 101 to 200 homes or acres | 2 |
| 201 to 400 homes or acres | 3 |
| More than 400 homes or acres | 4 |
Each park would be at least 3,200 square feet, central and reachable by sidewalk. Each would have two accessible parking spaces and no other parking.
Also on the agenda
The full agenda also includes:
- design waivers for the Holiday Inn & Suites at 75 Belinda Parkway and MSR Plaza at 3007 N. Mt. Juliet Road
- a site plan for Carlson Properties at 9601 and 9619 Lebanon Road
- the E Division Business Park plan at 2062 E. Division St.
- a preliminary plat for McFarland Farms Phase 3 at 5238 Old Lebanon Dirt Road
- releasing $352,043.42 in letters of credit for Groves Reserve Phases 1 and 2
What it means for you
- Speak at the meeting. Citizen comments come early on the agenda, at 6:30 p.m. Thursday, Nov. 19, in the Commission Chambers at City Hall.
- Neighbors on E. Division Street: the four waivers decide how wide the open yard and buffers next to homes will be, and whether a wall can stand inside the yard.
- The board decides. Every item marked for the Board of Commissioners still needs the board’s votes before it takes effect.
Have your say